Ministry of Defence – United Kingdom, Poland, LENP

  • Arctic Sleeping bags (-30 degrees) 12,000
  • Arctic Bivvy Bags 12,000
  • Thick Roll Mats 12,000
  • Waterproof stuff bags 12,000

Timing: 7 weeks, shipments every 2 weeks

 

Overview: It was announced that the UK would send 12,000 sleeping kits to the Ukrainian Armed Forces to assist them in grueling winter conditions. Suppliers, however, had lead times of 6-12 months on the sleeping systems, and the MOD needed them in 12 weeks. Once DE&S and MOD had successfully validated our product, we used one of our contracted factories to successfully supply and ship the product. We carried out third-party inspections during production and carried out a final pre-shipment inspection for every shipment per week. Working closely with our factories, we enabled fast and efficient deliveries to be made to the UK MOD. This, in turn, allowed the MOD to fulfil the promise of the government to the Ukraine, on time, and in full for the Ukrainian winter period.